A point machine (PM) is used to move a railway track to divert trains onto a desired track. The Miro PCM-Pneumatic (PCM-P) is a system designed to monitor the performance of a pneumatic PM. See Fig. 1.
Pressurised air is used to drive the mechanism that moves the rails. See Fig. 2. Once the rails have reached the desired position, the air flow stops. The PCM-P continuously measures the pneumatic pressure and flow rate and derives performance metrics.
A reference operation is determined after the PCM-P undergoes a thirty-operation training phase. Every subsequent operation is then compared to the reference operation and is classified as ‘Good’, ‘Possible Issue’ or ‘Critical’ to indicate the severity of the operation. The user can configure the system to send alerts and alarms, based on the severity level.
The PCM-P provides real-time insights into point operations, detects impending failures and notifies maintenance crews via emails or SCADA alerts. This enables proactive remedial action to be taken, before a catastrophic failure causes disruption of services, impacting the rail network and customers. This results in improved reliability, cost savings, and increased customer goodwill.
The metrics captured by the PCM-P allows network operators to transition from a periodic based maintenance to condition based maintenance, not only reducing operational costs, but also helping operators manage track access and downtime.
A proprietary database solution, AsMoSys (Asset Monitoring System) is used to import, view and manage PCM data, including emailing notifications.
This case study illustrates how the PCM alerted users to a pneumatic hose leak and subsequent resolution.
At 08:48 hrs, the PCM-P at Site 518 detected an operation with an unusually long run time, with a continuous flow of around 0.5L/s at the end of the operation. See Figure 3 below.
Figure 4 shows the point operation five hours later also indicating the flow continuing after the end of the operation.
Eventually, at 20:56, 12 hours after first identifying the extended run time, the point operation failed with continued flow (indicating a leak) and the subsequent pressure level too low to complete the point operation. See Figure 5.
Figure 5 – PCM-P Point operation graph at 2020-04-20 20:56 Hrs
The maintenance crew discovered a rat had bitten into one of the pneumatic lines. See figure 6. This was the source of the air leak, resulting in the point machine eventually failing.
The AsMoSys Event list shows the Critical Event for PCM Site 518 occurring at 08:48. See Figure 7 below. Critical events will result in an email being sent to the authorised users.
Figure 7 – Event list for PCM Site 518
Following the repair, the point returned to their normal “good” state at 21:36 on 20-04-2020, as shown in Figure 8.
Figure 8 – PCM-P Point operation graph at 2020-04-20 21:36 – following repair
Figure 9 below shows the event list during the repair with the good operation occuring at 21:36, after completion of repair.
The Miro PCM system was able to provide alerts for the leaking hose, and the point failure could have been prevented if immediate attention had been taken to replace the leaking hose.